Overview

Scope of work

1. Solar Photovoltaic System

    • Structural steel works
    • Supply and install Solar Panel
    • Supply and install Grid Connected Inverter
    • Supply and install AC Power Distribution Panel
    • Supply and install AC Combiner Box
    • Supply and install Ambient Detector Unit
    • Supply and install System Monitor
    • Cabling Works
    • Testing & Commissioning
2. Biogas System

    • Supply and install Biogas Desulfurizing Tower
    • Supply and install Biogas Pre-treatment System
    • Supply and install biogas genset
    • Supply and install Biogas Flare Unit
    • Supply and install Water heater
    • Supply and install Gas Holder
    • Testing & Commissioning
  • Status Completed
  • Completion Date July 2015
  • Location Kuala Lumpur
  • Type Renewable energy
  • ClientBEWG (M) Sdn. Bhd.
  • DistrictPantai Dalam
  • Start DateJuly 2011
  • CapacitySolar Panel = 200 kWh; Biogas = 700 kWh
  • LESB RolesMain Sub-Contractor
  • ValueRM 70,000,000.00