Overview

Scope of work

1. Soil & Site Investigation
2. Environmental Management Plan
3. River Improvement Works

  • Earthwork & Site Preparation
  • River Alignment & Improvement Works
  • Gabion Wall Protection
  • Slope Protection
4. Relocation of Utilities
5. Treated Effluent Detention Pond

  • Piling
  • Pond Structure
  • Process MBE Works
6. Testing and Commissioning
  • Status Completed
  • Completion Date April 2024
  • Location Perak
  • Type River Engineering
  • ClientJabatan Perkhidmatan Pembetungan
  • DistrictPapan
  • Start DateMarch 2023
  • Capacity900 Meter
  • LESB RolesMain Contractor (Design & Build)
  • ValueRM 13,304,441.53

Gallery

Enquiry