Overview

Scope of work

1. Mechanical Works

  • Treated Water Pumping System
  • Flowmeter
  • Plunger, Altitude, Butterfly Valve
  • Surge Protection System Drainage Pumping System
  • Overhead Crane
  • Re-chlorination System
2. Electrical Works

  • Main Switchboard
  • Cabling Works
  • Small Power & Lighting Works
  • LV Sub Control & Cabling Works
  • Waterproof Local Control Panel (LCP)
  • Level Sensor
  • Control & Telemetry Works
  • Lightning Protection & Earthing System
  • Status Completed
  • Completion Date August 2021
  • Location Terengganu
  • Type Mechanical & Electrical
  • ClientBEWG (M) Sdn. Bhd.
  • DistrictKemaman
  • Start DateDecember 2015
  • Capacity10 MLD
  • LESB RolesMain Sub-Contractor
  • ValueRM 6,600,000.00